Demolition in Monument runs through two separate approval tracks that have to be resolved before the first wall comes down. Pikes Peak Regional Building Department (PPRBD) issues the wrecking or demolition permit itself, while the Colorado Department of Public Health and Environment (CDPHE) controls the asbestos question that sits in front of nearly every teardown in an older home. Apollo Construction treats those as two separate decisions, made in the right order, rather than one generic “demo permit” checkbox.
A Wrecking Permit Is Required to Remove a Structure
PPRBD requires a wrecking permit whenever an entire structure is being removed; interior, non-load-bearing demolition is treated as a different scope and may call for a separate interior demolition permit instead. To obtain the wrecking permit, PPRBD requires a licensed wrecking contractor’s ID number, insurance documentation that specifically includes XCU coverage — explosion, collapse, and underground — proof of utility cutoff (gas and electric) from the appropriate utility purveyor, and a CDPHE permit for asbestos and debris removal.
That utility-cutoff proof is not a formality PPRBD glosses over. We confirm gas and electric disconnection with the utility provider before the permit application goes in, because a wrecking permit application without it simply doesn’t move.
Asbestos Inspection Comes Before Anything Else Is Disturbed
CDPHE requires notification for essentially all demolitions, and a certified Asbestos Building Inspector — employed by a CDPHE-registered consulting firm — has to inspect the structure before renovation or demolition begins, or the material has to be assumed asbestos-containing and handled accordingly. A Demolition Notification Application goes to CDPHE even when the inspection finds nothing, along with the notification fee.
That filing carries a standard 10-working-day notification period before demolition can start, though a waiver of that waiting period can be requested from CDPHE directly. Where the abatement scope involves friable asbestos-containing material above the regulatory trigger levels in an area of public access, CDPHE requires a full permit, not just notification. We build that 10-day window into the schedule from the first site visit, because it’s the single most common reason a Monument demolition start date slips.
Site Disturbance Can Pull In a Separate Stormwater Permit
Larger demolition scopes can trigger a Grading and Erosion Control (GEC) Permit from the City of Colorado Springs Stormwater Enterprise — the agency that also covers Monument-area drainage review. That permit applies if the disturbance reaches 1 acre or more (counting multiple parcels in a common plan of development), if the work sits in a Streamside overlay zone, or if it impacts an open drainage channel as determined by the review engineer. Most single-lot residential demolition in Monument stays well under that acreage threshold, but we check the overlay-zone map before ruling it out on a larger lot.
As part of the permit process, PPRBD’s standard practice is to notify outside agencies — the El Paso County Health Department, City of Colorado Springs Stormwater, and Colorado Springs Utilities — that a demolition permit has been issued, with the permit holder responsible for getting Health Department and Stormwater sign-off before the final inspection. We confirm the current agency routing with PPRBD directly for each project rather than assuming a fixed list.
Town of Monument Adds Its Own Dust-Control Layer
Separate from PPRBD’s building-permit process, the Town of Monument lists “Demolition/Dust Control” as a permit item under shared Town and PPRBD jurisdiction, and any contractor working within Town limits needs a current Town of Monument business license in addition to the PPRBD wrecking or demolition permit. We hold both before mobilizing a crew, not just the PPRBD paperwork.
No official Town of Monument historic-district or landmark-review program was located in our research, so we do not represent demolition in Monument as triggering a historic review — if a specific property has a deed restriction or covenant along those lines, that’s a separate question from the Town’s own code.
Structural Conditions Get Resolved, Not Guessed At
Opening a wall or ceiling during demolition can reveal a bearing condition, a header, or a connection that wasn’t visible during estimating. We stop, protect the area, and get the applicable design direction before a load-affecting removal continues — appearance alone isn’t how a bearing wall gets identified. The same discipline applies to concrete and masonry: unexplained cracking or movement gets investigated before force is applied to it.
That pause protects the schedule more than it costs it. A limited demolition scope that turns into an unplanned structural repair is far more disruptive than a documented stop, a quick engineering call, and a resumed sequence with the right direction in hand.
How We Sequence a Monument Demolition Project
We start with the address, the removal scope, and whether the structure or an addition to it predates the materials most likely to contain asbestos. The CDPHE inspection is scheduled first, because its outcome and the 10-day notification clock set the earliest possible start date for anything else. In parallel, we confirm utility disconnection proof and pull the PPRBD wrecking or interior demolition permit, and check GEC and Town dust-control requirements against the project’s footprint.
Once permits and the notification window clear, removal proceeds in a controlled sequence: contents and loose material first, finishes next, then framing and structural elements, with material streams kept separate for disposal. Closeout confirms the stop line matches what was agreed, documents any condition discovered along the way, and leaves the site ready for the next trade or final grading.
Demolition Near Monument
Same crew, neighbouring jurisdictions. Permit rules differ by city — pick yours.
- Demolition in Colorado Springs
- Demolition in Castle Rock
- Demolition in Castle Pines
- Demolition in Parker
- Demolition in Lone Tree
Demolition in Other Front Range Cities
Apollo handles demolition across the Front Range. Each city page below covers that city’s own permit office, code edition and local conditions.
- Demolition in Arvada
- Demolition in Aurora
- Demolition in Boulder
- Demolition in Centennial
- Demolition in Cherry Hills Village
- Demolition in Commerce City
- Demolition in Denver
- Demolition in Englewood
- Demolition in Erie
- Demolition in Evergreen
- Demolition in Federal Heights
- Demolition in Golden
- Demolition in Greenwood Village
- Demolition in Highlands Ranch
- Demolition in Ken Caryl
- Demolition in Lafayette
- Demolition in Lakewood
- Demolition in Littleton
- Demolition in Longmont
- Demolition in Louisville
- Demolition in Northglenn
- Demolition in Superior
- Demolition in Thornton
- Demolition in Westminster
- Demolition in Wheat Ridge
- Demolition in Sheridan
- Demolition in Edgewater
- Demolition in Morrison
- Demolition in Columbine Valley
- Demolition in Manitou Springs
- Demolition in Glendale
- Demolition in Elizabeth
- Demolition in Idaho Springs
- Demolition in Black Forest
- Demolition in Falcon & Peyton
- Demolition in Franktown
- Demolition in Georgetown
- Demolition in Empire
- Demolition in Palmer Lake
- Demolition in Larkspur
- Demolition in Foxfield
- Demolition in Sedalia
- Demolition in Byers
- Demolition in Black Hawk
- Demolition in Central City
- Demolition in Rollinsville
- Demolition in Cripple Creek
- Demolition in Victor
- Demolition in Broomfield
Other Apollo Services in Monument
These Monument guides cover the other projects we plan and build, with the permit path for each. For every other trade, see all Apollo services in Monument.
- Kitchen Remodeling in Monument — cabinets, counters, layout changes and permits
- Bathroom Remodeling in Monument — showers, tubs, vanities, tile and waterproofing
- Basement Finishing in Monument — egress, framing, insulation, permits and finish work
- Home Additions in Monument — room additions, bump-outs, structural and permit planning
- Roofing in Monument — reroofing, tear-off, underlayment and inspections
- Deck Building in Monument — decks, footings, guards, stairs and permits
- Fence Installation in Monument — wood, composite and metal fences, heights and setbacks
- Framing in Monument — walls, beams, load-bearing changes and engineering
- Drywall in Monument — hanging, finishing, fire-rated assemblies and repair
- Tile Installation in Monument — floors, showers, backsplashes and waterproofing
- Painting in Monument — interior and exterior prep, lead-safe work and finish
- Siding in Monument — fiber cement, LP and vinyl siding, full re-side
- Concrete in Monument — driveways, patios, walkways and flatwork
Related Pages
Common Questions
Do I need a permit to demolish a structure in Monument?
Yes. PPRBD requires a wrecking permit for removing an entire structure, or an interior demolition permit for non-load-bearing interior work, and the Town of Monument separately lists demolition and dust control as a shared permit item.
How long does the asbestos process add to the schedule?
CDPHE’s standard notification period is 10 working days after the Demolition Notification Application is filed, following the required inspection by a certified Asbestos Building Inspector. A waiver of that period can be requested from CDPHE in specific cases.
Does my utility need to be disconnected before demolition starts?
Yes. PPRBD requires proof of gas and electric utility cutoff from the appropriate utility provider as part of the wrecking permit application, before the permit is issued.
Will demolition disturb my whole lot in Monument?
Usually not for a single-residence scope. A Grading and Erosion Control Permit is only triggered at 1 acre or more of disturbance, a Streamside overlay zone, or an impacted drainage channel, which most residential demolition in Monument falls well under.
Talk to Us About Your Project
Tell us what’s coming down, the age of the structure, and whether the home will stay occupied during the work. We’ll schedule the CDPHE inspection early, confirm utility disconnection, and line up the PPRBD and Town permits so the 10-day notification window is the pace-setter, not a surprise.