Demolition in Cripple Creek carries two layers of rules that do not show up in most towns at once: a statewide asbestos program that applies to every demolition regardless of the building’s age, and a City permit process that screens every application through Historic Preservation before it moves forward. Apollo Construction builds both steps into the schedule from the first walkthrough, not as an afterthought once the dumpster is already on site.
Asbestos Applies to Every Demolition, Not Just Old Buildings
Colorado’s Air Quality Control Commission Regulation 8, Part B, administered by the Colorado Department of Public Health and Environment, requires an asbestos inspection by a Colorado-certified Asbestos Building Inspector before any demolition begins — and this applies regardless of the structure’s apparent condition or age. A narrow exception exists only for portions of a building constructed after October 12, 1988, and only with documented due diligence showing no asbestos-containing material was used.
For single-family residential dwellings, the trigger levels that require removal by a Colorado-certified General Abatement Contractor before disturbance are 50 linear feet on pipes, 32 square feet on other surfaces, or the volume of a 55-gallon drum. Commercial and public buildings carry higher thresholds — 260 linear feet and 160 square feet — but the inspection requirement itself does not change based on building size.
Notification Is Required Even With No Asbestos Found
This is the part that surprises people most: CDPHE requires a Demolition Notification Application to be filed even when the inspection finds no asbestos at all. The notification, along with its fee, has to reach the state’s Air Pollution Control Division at least 10 working days before demolition starts, with limited allowance for expedited handling in genuine emergencies. Skipping this step because a building looks clean is one of the most common — and most costly — mistakes on a demolition job anywhere in Colorado.
Materials bonded with or contaminated by asbestos above trigger levels, such as certain floor tile, mastic, or tar-impregnated roofing, cannot simply be crushed, jackhammered, or recycled once demolition begins; state rules require they be removed in large sections without rendering them friable. We treat this as a planning input, not a field surprise, by lining up the inspection and abatement contractor before any equipment is scheduled.
City Permits and the Historic Preservation Review
Cripple Creek routes every building permit application — demolition included — through its Historic Preservation Director first, to determine whether Historic Preservation Commission review and a Certificate of Appropriateness are also required. This matters most for anything inside or near the National Historic Landmark core, where the City’s working design standard traces back to the 1988 Architectural Guidelines for Cripple Creek and where facade preservation is a common outcome even on projects that are otherwise a full teardown.
Because the specific boundary lines and demolition-delay provisions for the historic district were not something we could confirm in detail from the sources available to us, any demolition inside or near the historic core should have its address checked directly with the Historic Preservation Director before a firm demolition date is set. We build that confirmation step into the schedule rather than assuming a property falls outside review.
Utility Disconnects and Site Safety
Before any structural demolition begins, active utility lines — buried and overhead — have to be identified and disconnected in coordination with the relevant utility providers. As a matter of standard statewide practice, and one we follow on every demolition regardless of scope, we request a utility locate through Colorado 811 well ahead of any excavation or foundation removal tied to the demolition, so buried lines are marked before equipment moves onto the site.
On sites large enough to trigger it — commercial demolition or residential demolition on four or more units — Cripple Creek’s construction-activity ordinance requires an approved dust suppression plan before a permit issues, along with a rule that any material tracked onto a City street be cleared within two hours of the day’s last trip. Smaller residential demolition is not formally required to file that plan, but dust and debris control at this elevation, where wind speed is a real design factor, is something we manage as standard practice regardless of project size.
Debris, Recycling, and What Cannot Be Assumed
Once asbestos clearance is documented, demolition debris handling follows the City’s adopted building code and standard construction waste practice; a Cripple Creek-specific ordinance section naming demolition fee amounts or a separate local demolition-permit process beyond the adopted International Building Code was not something we could locate and confirm, so that detail should be verified directly with the Building Department for any given project rather than assumed from general code language.
What is confirmed is that local building-code amendments do not appear to touch the demolition chapter itself, meaning demolition on a Cripple Creek project generally follows the adopted International Building Code’s demolition provisions as written, layered under the state asbestos rules described above. Where a code edition or a figure is not locally amended, we treat the base adopted code as the standard and flag anything uncertain for office confirmation before work proceeds.
How We Sequence a Cripple Creek Demolition
The sequence starts with the asbestos inspection by a Colorado-certified inspector, regardless of the building’s age, because every other step depends on that result. In parallel, we confirm whether the address sits inside the historic-review boundary and get that answer from the Historic Preservation Director before setting a firm start date. The CDPHE Demolition Notification Application goes in next, with its 10-working-day clock running before any wrecking begins, alongside the separate City building permit for the demolition itself.
Utility disconnects and the Colorado 811 locate happen before equipment mobilizes, not the week of. If asbestos-containing material above trigger levels is found, abatement by a certified General Abatement Contractor happens before general demolition starts, and affected materials are removed intact rather than crushed. Dust control, street cleanup, and debris hauling close out the physical work, and any fee or process detail we could not confirm from official sources is checked with the City before it is built into the client’s schedule or budget.
Demolition Near Cripple Creek
Same crew, neighbouring jurisdictions. Permit rules differ by city — pick yours.
- Demolition in Victor
- Demolition in Manitou Springs
- Demolition in Colorado Springs
- Demolition in Monument
- Demolition in Palmer Lake
Demolition in Other Front Range Cities
Apollo handles demolition across the Front Range. Each city page below covers that city’s own permit office, code edition and local conditions.
- Demolition in Arvada
- Demolition in Aurora
- Demolition in Black Forest
- Demolition in Black Hawk
- Demolition in Boulder
- Demolition in Byers
- Demolition in Castle Pines
- Demolition in Castle Rock
- Demolition in Centennial
- Demolition in Central City
- Demolition in Cherry Hills Village
- Demolition in Columbine Valley
- Demolition in Commerce City
- Demolition in Denver
- Demolition in Edgewater
- Demolition in Elizabeth
- Demolition in Empire
- Demolition in Englewood
- Demolition in Erie
- Demolition in Evergreen
- Demolition in Falcon & Peyton
- Demolition in Federal Heights
- Demolition in Foxfield
- Demolition in Franktown
- Demolition in Georgetown
- Demolition in Glendale
- Demolition in Golden
- Demolition in Greenwood Village
- Demolition in Highlands Ranch
- Demolition in Idaho Springs
- Demolition in Ken Caryl
- Demolition in Lafayette
- Demolition in Lakewood
- Demolition in Larkspur
- Demolition in Littleton
- Demolition in Lone Tree
- Demolition in Longmont
- Demolition in Louisville
- Demolition in Morrison
- Demolition in Northglenn
- Demolition in Parker
- Demolition in Rollinsville
- Demolition in Sedalia
- Demolition in Sheridan
- Demolition in Superior
- Demolition in Thornton
- Demolition in Westminster
- Demolition in Wheat Ridge
- Demolition in Broomfield
Other Apollo Services in Cripple Creek
These Cripple Creek guides cover the other projects we plan and build, with the permit path for each. For every other trade, see all Apollo services in Cripple Creek.
- Kitchen Remodeling in Cripple Creek — cabinets, counters, layout changes and permits
- Bathroom Remodeling in Cripple Creek — showers, tubs, vanities, tile and waterproofing
- Basement Finishing in Cripple Creek — egress, framing, insulation, permits and finish work
- Home Additions in Cripple Creek — room additions, bump-outs, structural and permit planning
- Roofing in Cripple Creek — reroofing, tear-off, underlayment and inspections
- Deck Building in Cripple Creek — decks, footings, guards, stairs and permits
- Fence Installation in Cripple Creek — wood, composite and metal fences, heights and setbacks
- Framing in Cripple Creek — walls, beams, load-bearing changes and engineering
- Drywall in Cripple Creek — hanging, finishing, fire-rated assemblies and repair
- Tile Installation in Cripple Creek — floors, showers, backsplashes and waterproofing
- Painting in Cripple Creek — interior and exterior prep, lead-safe work and finish
- Siding in Cripple Creek — fiber cement, LP and vinyl siding, full re-side
- Concrete in Cripple Creek — driveways, patios, walkways and flatwork
Related Pages
Common Questions
Does every demolition in Cripple Creek need an asbestos inspection?
Yes. Colorado’s Regulation 8, Part B requires an asbestos inspection by a Colorado-certified inspector before any demolition, regardless of the building’s age or apparent condition, with only a narrow exception for documented post-1988 construction.
If the inspection finds no asbestos, is notification still required?
Yes. A Demolition Notification Application must be filed with the state at least 10 working days before demolition begins, even when no asbestos is found. This applies to every demolition of every facility under state rules.
Will a demolition in the historic district need extra approval?
Possibly. Every Cripple Creek building permit application, including demolition, is first reviewed by the Historic Preservation Director to determine whether Historic Preservation Commission approval is also required. We confirm this with the City for any address inside or near the historic core before scheduling work.
Are utilities disconnected before demolition starts?
Yes. Active utility lines are identified and disconnected ahead of structural demolition, and we request a utility locate through Colorado 811 before any excavation or foundation removal begins.